Tropical Chevrolet, 09-12-23 UES No 15409 SPECIAL insp rept #042 (structural steel connections) - GDZProject No.: 2110.2100049 Report No.: 15409 Date: September 12, 2023 8050 NW 77th Court · Miami, FL 33166 · P: 305.249.8434 · F: 305.249.8479 STRUCTURAL OBSERVATION REPORT No. SPECIAL-042 CN: GDZ Page 1 of 3 cc: 1 − Job Site; 1 − Client; 1 The Original of this Report was Signed and Impressed Sealed by the Above Registered Engineer in Accordance with Rule 21H-18.11, Chapter 471, Florida Statute Client: Lebolo Construction Management, Inc. 2100 Corporate Drive Boynton Beach, FL 33426 Project: Tropical Chevrolet Renovation/Expansion 8880 Biscayne Blvd. Miami Shores, FL 33138 Agent: Gaetano Di Zio, E.I. Date of Services: 09/12/2023 Village of Miami Shores Building Permit No: CC-12-20-2951 (issued date 11/07/22, expires 05/08/23) Scope of Field Services: Professional observation of completed structural elements (Special Inspector). Reference Documents: • JSG structural drawings sheets S1.0 thru S4.2 (15 pages), Bulleting 7 dated 07/21/2022, signed/sealed by Mark Johnson FL-PE#51983, reviewed/approved for structural compliance by the Village of Miami Shores Bldg. Dept. on 08/22, (permit set review by the Miami-Dade County Department of Regulatory and Economic Resources on 05/16/2022). • SUNCOR, Inc. structural steel erection/fabrication shop drawings sheets AB1 thru TP101 (total of 219 pages) dated 04/13/2022 (Rev. A – Issued for Approval) Submittal #051200-5.0 (Structural Steel Shop Drawings), reviewed for compliance (stamped “Reviewed as Noted - Make Corrections”) by JSG on 05/03/2022. • Canam Steel Corporation (CSC) steel metal deck shop drawings sheets DE1.1 thru DE2.1 (total of 3 pages) dated 04/08/2022 (Issued for Approval) Submittal #051200-6.0 (Deck Shop Drawings), reviewed for compliance (stamped “Reviewed as Noted - Make Corrections”) by JSG on 04/15/2022. Record of Field Observations: 1. Visual verification of the structural steel connections at the following locations indicated below: a) ½” Ø x 1½” shear studs welded connections to the proposed new C10x25 steel channels approx. between grids “C.5” thru “D.5” and lines “5.5” thru “6.5 for the precast concrete double “T’s” repair on the roof at the existing service department, as per the attached Conemco Engineering, Inc. precast concrete double Tee’s structural repair drawings, as we addressed on UES Structural Observation Reports No. 38 (No.: 10040) dated 07/07/2023 and No. 41 (No.: 14712) dated 09/06/2023, re−inspection inconclusive – pending current welder qualification certification: ➢ Welding slag was not completely removed from locations that require Visual Testing (VT). ➢ Incomplete or undersize fillet welds. ➢ Missing three (3) shear studs at locations marked in the field. ➢ A couple of shear studs were found to be spaced more than 8” o.c. The structural steel connections at the locations mentioned above were found not to be inconclusive. The welder qualification certificate was provided during our site visit on 07/27/2023, however current continuity paperwork pending for review (Period of Effectiveness). The welder that performed the work was not available onsite in order to verify his welder qualification. As per The Structural Welding Code: 6.2.3 Period of Effectiveness 6.2.3.1 Welders and Welding Operators. The welder’s or welding operator’s qualification as specified in this code shall be considered as remaining in effect indefinitely unless: (1) the welder is not engaged in a given process of welding for which the welder or welding operator is qualified for a period exceeding six months, or (2) there is some specific reason to question a welder’s or welding operator’s ability (see 6.25.1). 2. Visual verification of drilled holes for the post-installed expansion anchors at the following locations indicated below: DRAFT Project No.: 2110.2100049 Report No.: 15409 Date: September 12, 2023 8050 NW 77th Court · Miami, FL 33166 · P: 305.249.8434 · F: 305.249.8479 STRUCTURAL OBSERVATION REPORT No. SPECIAL-042 CN: GDZ Page 2 of 3 cc: 1 − Job Site; 1 − Client; 1 The Original of this Report was Signed and Impressed Sealed by the Above Registered Engineer in Accordance with Rule 21H-18.11, Chapter 471, Florida Statute a)Cleanness/depth check (4” min. embedment) for the horizontal expansion anchors installation into existing CIP concrete roof beam at approx. gridlines D.6x11.5 and D.6x12 at the expansion building (Quick Lube room), as per attached SK 04-12-23 (Modified), completed. Mr. Jim Jenco, Project Superintendent with Lebolo Construction, was notified of the aforementioned visual verification results. Please see adjacent report pages for photographs, welder certification qualification, Conemco Engineering shop drawings and SK 04-12-23. DRAFT Project No.: 2110.2100049 Report No.: 15409 Date: September 12, 2023 8050 NW 77th Court · Miami, FL 33166 · P: 305.249.8434 · F: 305.249.8479 STRUCTURAL OBSERVATION REPORT No. SPECIAL-042 CN: GDZ Page 3 of 3 cc: 1 − Job Site; 1 − Client; 1 The Original of this Report was Signed and Impressed Sealed by the Above Registered Engineer in Accordance with Rule 21H-18.11, Chapter 471, Florida Statute Reviewed by: Universal Engineering Sciences Certificate of Authorization No. 549 Carlos Naumann, P.E., S.I. Florida Professional Engineer No. 18594 Florida Special Inspector No. 181 DRAFT DRAFT THIS SET OF DRAWINGS SHOULD NOT BE SCALED; USE DIMENSIONS AND INFORMATION SHOWN. PRIOR TO PROCEEDING WITH ANY WORK AND FABRICATION, THE CONTRACTOR SHALL: VERIFY AND COORDINATE WITH ANY ARCHITECTURAL DRAWINGS FOR ALL DIMENSIONS AND ELEVATIONS SHOWN OR NOT SHOWN ON THE SHORING DRAWINGS. ANY DIMENSIONAL DISCREPANCY FOUND ON THE SHORING DRAWINGS SHALL BE CONTROLLED BY THE DIMENSIONS INDICATED ON THE ARCHITECTURAL DRAWINGS. CONTRACTOR SHALL FURTHER VERIFY AND CONFIRM WITH THE ARCHITECT AND THE STRUCTURAL ENGINEER FOR RESOLUTION OF SUCH DISCREPANCY. VERIFY ALL EXISTING CONDITIONS AT THE JOB SITE, PROTECT AND MAINTAIN ALL EXISTING STRUCTURES, UTILITIES, FACILITIES AND THEIR CONTENTS. THE GENERAL CONTRACTOR SHALL AT ALL TIMES MAINTAIN AT THE JOBSITE A CURRENT APPROVED SET OF DRAWINGS. GENERAL CONDITIONS THE STRUCTURAL COMPONENTS FOR THIS PROJECT HAVE BEEN DESIGNED IN COMPLIANCE WITH THE FLORIDA BUILDING CODE (FBC) 2020. THE FOLLOWING LOADS HAVE BEEN USED FOR THE STRUCTURAL DESIGN OF THE BUILDING: GRAVITY LOADS: DEAD LOADS: 3" CONCRETE TOPPING CONCRETE JOISTS SELF-WEIGHT LIVE LOAD: ROOF = 100 PSF DESIGN CRITERIA CONCRETE CHIPPING IS ALLOWED ONLY IF APPROVED BY THE ENGINEER OF RECORD. DO NOT CHIP OR DEMOLISH CONCRETE WITHOUT THE ENGINEER'S APPROVAL. 1. CONCRETE. QUICKCRETE 5000 OR APPROVED EQUAL APPLIED IN MULTIPLE LIFTS. MINIMUM THICKNESS 18" IN AND NO MORE THAN 3", CHECK MANUFACTURER PRODUCT USE, SITE PREPARATION, MIXING AND APPLICATION. AVOID CONTACT WITH ALUMINUM TO PREVENT ADVERSE CHEMICAL REACTION AND POSSIBLE PRODUCT FAILURE. INSULATE POTENTIAL AREAS OF CONTACT BY COATING ALUMINUM BARS, RAILS, POST ETC. WITH AN APPROPRIATE EPOXY SUCH AS SIKADUR HI-MOD 32. 2. JOINTS REPAIR. SIKAFLEX 2C NS (POLYURETHANE BASED ELASTOMERIC SEALANT), OR APPROVED EQUAL, FOR HORIZONTAL AND VERTICAL JOINTS. CHECK THE MANUFACTURER PRODUCT USE, JOINT PREPARATION, MIXING AND APPLICATION. 3. WATERPROOFING SYSTEM ZINSSER WATERTITE WATERPROOFING SYSTEM, OR APPROVED EQUAL. CHECK MANUFACTURER PRODUCT USE, SITE PREPARATION, MIXING AND APPLICATION. CONTRACTOR TO MATCH ANY CONCRETE REPAIR AREAS TO EXISTING ARCHITECTURAL FEATURES. CONCRETE REPAIR PRODUCTS SHALL BE APPLIED ON A SATURATED SURFACE DRY TO AVOID RAPID DRYING AND WEAKENING OF THE PRODUCT AND ITS BOND TO THE SURFACE. CONCRETE REPAIR SHORING FORMS AND SHORES FOR CONCRETE SLABS AND BEAMS SHALL BE DESIGNED TO WITHSTAND THE DEAD LOAD OF CONCRETE AND ANTICIPATED CONSTRUCTION LOADS. IN NO CASE SHALL THE SLAB, WALL OF BOTTOM BEAM FORMS BE STRIPPED EARLIER THAN 5 DAYS AFTER PLACEMENT AND UNTIL THE COMPRESSIVE STRENGTH OF 4,000 PSI HAS BEEN ATTAINED. DESIGN AND CONSTRUCTION OF FORM WORK AND SHORING SHALL COMPLY WITH THE A.C.I. 318 BUILDING CODE AND BE ENTIRELY THE RESPONSIBILITY OF THE GENERAL CONTRACTOR. SHORING DRAWINGS TO BE PROVIDED BY GENERAL CONTRACTOR AND SHALL BE SIGNED AND SEALED BY A PROFESSIONAL ENGINEER REGISTERED IN THE STATE OF FLORIDA. SHALL BE DEFORMED BARS, FREE FROM LOOSE RUST AND SCALE, AND CONFORMING TO A.S.T.M. A615 GRADE 60. ALL ACCESSORIES SHALL HAVE UPTURNED LEGS, AND BE PLASTIC DIPPED AFTER FABRICATION. ACCESSORIES FOR REINFORCING SHALL BE INSTALLED IN ACCORDANCE WITH A.C.I. 315 CURRENT EDITION. ALL PLACEMENT OF REINFORCING BARS SHALL BE IN ACCORDANCE WITH THE MANUAL OF STANDARD PRACTICE OF THE CONCRETE REINFORCING STEEL INSTITUTE. PLASTIC TIPPED COLUMN SPACERS SHALL BE PROVIDED FOR VERTICAL COLUMN REINFORCING STEEL, SUCH THAT A 1 1/2" MINIMUM CLEARANCE IS MAINTAINED. AS PER FBC 2020 R606.2.13, MASONRY JOINT REINFORCEMENT IN EXTERIOR WALLS OR INTERIOR WALLS EXPOSED TO MOIST ENVIRONMENT AND WEATHER SHALL BE HOT-DIPPED GALVANIZED AND COMPLY WITH ASTM A 153, CLASS B-2. BAR DEVELOPMENT AND LAP SPLICE LENGTH CONTRACTOR MAY LAP SPLICE STEEL REINFORCING BARS AT LOCATIONS OF HIS CHOOSING EXCEPT FOR THE FOLLOWING: 1. LONGITUDINAL BEAM TOP BARS AND CONCRETE SLAB TOP BARS SHALL BE SPLICED AT MID SPAN. 2. LONGITUDINAL CONCRETE BEAM BOTTOM BARS AND CONCRETE SLAB BOTTOM BARS SHALL BE SPLICED AT SUPPORT(S). ALL STEEL REINFORCING LAP SPLICES, UNLESS INDICATED OTHERWISE, SHALL SATISFY THE FOLLOWING: REINFORCING STEEL LAP SPLICE SCHEDULE BAR SIZE #3 #4 #5 #6 #7 #8 #9 #10 #11 TOP BAR * 2'-2"2'-10" 3'-6" 4'-3" 6'-0" 6'-9" 7'-8" 8'-6" 9'-4" OTHER 1'-8"2'-2"2'-8" 3'-3" 4'-8" 5'-2" 5'-10" 6'-6"7'-2" DEVELOPMENT LENGTH SCHEDULE BAR SIZE #3 #4 #5 #6 #7 #8 #9 #10 #11 TOP BAR *1'-6"2'-2"2'-8" 3'-3" 4'-8" 5'-2" 5-10" 6'-6"7'-2" OTHER 1'-3" 1'-8"2'-1"2'-6" 3'-6" 4'-0" 4'-6" 5'-0" 5'-6" ALL STEEL REINFORCING BAR DEVELOPMENT LENGTHS, UNLESS INDICATED OTHERWISE, SHALL SATISFY THE FOLLOWING: MINIMUM CONCRETE COVER TO REINFORCING STEEL IN ACCORDANCE WITH ACI 318-14 AND SHALL BE AS FOLLOW: CONCRETE COVER ELEMENT BOTTOM TOP SIDE FOUNDATION 3"2"2" COLUMN/WALL --1-1/2" SLAB ON GRADE 2"1"- SHALL BE A MIX DESIGNED IN ACCORDANCE WITH A.C.I. 301 (LATEST EDITION) TO ACHIEVE A 28-DAY COMPRESSIVE STRENGTH OF 4,000 P.S.I. AND A MAXIMUM WATER-CEMENT RATIO OF 0.45 AND A SLUMP OF 4"+ 1". ALL CONCRETE SHALL CONTAIN AN ENGINEER-APPROVED A.S.T.M. C494 TYPE `D` ADMIXTURE (WATER-REDUCING RETARDED). TRANSPORTATION, PLACING, AND CURING OF CONCRETE SHALL COMPLY WITH A.C.I. 318 BUILDING CODE (LATEST EDITION). ALL CONCRETE STRUCTURAL COMPONENTS SHALL HAVE CONCRETE STRENGTH TESTED IN ACCORDANCE WITH A.S.T.M. STANDARDS, FLORIDA BUILDING CODE 2020 AND ACI 318-14. TESTING LAB SHALL PROVIDE COPIES OF CONCRETE TESTS RESULTS TO ENGINEERS OFFICE FOR REVIEW. CONCRETE MIX DESIGN SHALL BE SUBMITTED TO ENGINEER'S OFFICE FOR REVIEW. CONCRETE - ALL CONSTRUCTION SHALL COMPLY WITH THE F.B.C 2020 EXISTING AND ANY OTHER APPLICABLE CODES AND REGULATIONS - NOTIFY ENGINEER OF ANY DISCREPANCIES BETWEEN ACTUAL SITE CONDITIONS AND THOSE SHOWN ON THE PLANS AND OF ANY DISCRE- PANCIES WITHIN THESE PLANS. DO NOT CONTINUE WORK UNTIL THE ENGINEER HAS BEEN NOTIFIED - CONTRACTOR, BEFORE SUBMITTING BIDS, VISIT THE SITE, EXAMINE THE EXISTING STRUCTURES, NOTE ALL CONDITIONS AS TO CHARACTER AND EXTEND OF WORK INVOLVED - PROCURE AND PAY FOR ALL NECESSARY PERMITS OR CERTIFICATES REQUIRED TO COMPLETE THE WORK SHOWN OR SPECIFIED. MAKE ANY AND ALL REQUIRED NOTIFICATIONS AND COMPLY WITH ALL APPLICABLE FEDERAL, STATE, AND LOCAL ORDINANCES - EXECUTE ALL DEMOLITION WORK IN ORDERLY AND CAREFUL MANNER WITH DUE CONSIDERATION FOR ANY EXISTING STRUCTURES, INCLUDING ANY PARTS OF THE SURROUNDING AREAS WHICH ARE TO REMAIN. BARRICADE AND COVER AS NECESSARY TO PROTECT PEDESTRIANS, WORKMEN AND ADJACENT PROPERTIES - AVOID ANY ENCROACHMENT ON ADJACENT PROPERTIES. REPAIR AND MAKE GOOD ANY DAMAGE TO ADJOINING PROPERTIES OR IMPROVEMENTS CAUSED BY OPERATIONS,INCLUDING ANY DAMAGE OR LOSS TO ADJOINING TENANT OR PROPERTY OWNERS,WHETHER TO BUILDINGS,STOCKS OF MERCHANDISE,TRADE FIXTURES,OR THE LIKE - DISCONNECT ANY ELECTRIC, TELEPHONE, GAS, WATER, STEAM, OR OTHER LINES SERVICING THE STRUCTURE PER RULES AND REGULATIONS OF AUTHORITIES HAVING JURISDICTION,AS SPECIFIED,OR AS DIRECTED BY THE ENGINEER - REPAIR ALL DAMAGE TO SIDEWALKS OR PAVING CAUSED BY SITE WORK. SIDEWALKS AND CURBS MUST NOT BE PATCHED, BUT REPAIRED BY REPLACING ENTIRE SECTION - ALL MATERIAL REMOVED UNDER THIS CONTRACT, WHICH IS NOT TO BE SALVAGED OR REUSED, SHALL BECOME THE PROPERTY OF THE CONTRACTOR AND BE PROMPTLY REMOVED FROM THE SITE. DO NOT STORE OR PERMIT DEBRIS TO ACCUMULATE ON THE SITE - ON COMPLETION OF DEMOLITION WORK, LEAVE THE PROPERTY AND ADJACENT AREAS IN A CLEAN CONDITION, SATISFACTORY TO LOCAL AUTHORITIES AND THE ENGINEER - PROVIDE ALL NECESSARY SHORING, BRACING AND SUPPORT TO PREVENT MOVEMENT, SETTLEMENT OR COLLAPSE OF STRUCTURE OF ELEMENTS TO BE DEMOLISHED AND ADJACENT STRUCTURE OR ELEMENTS SHOWN TO REMAIN. SHORING AND BRACING SHALL BE DESIGNED BY CONTRACTOR'S PROFFESIONAL ENGINEER LICENSED IN THE APPLICABLY JURISDICTION. SUBMIT TO ENGINEER OF RECORD FOR REVIEW. DEMOLITION NOTES 1. WORKERS INVOLVED IN RESTORATION WORKS MUST BE PROVIDED WITH APPROPRIATE TRAINING, INSTRUCTIONS AND EXPERIENCE ON SIMILAR PROJECTS TO CARRY OUT RENOVATION / RESTORATION WORKS OF OCCUPIED BUILDINGS 2. CONTRACTOR SHALL BE RESPONSIBLE TO CONTINUOUSLY INSPECT ALL WORKERS FOLLOW ALL SAFETY MEASURES OR TO DESIGNATE A SAFETY MANAGER. 3. SAFETY MANAGER OR CONTRACTOR SHALL INSPECT PERSONAL PROTECTIVE EQUIPMENT BEFORE USE. 4. IF ELECTRICAL EQUIPMENTS SUCH AS DRILLS, HAMMERS, LIGHTS OR OTHERS ARE TO BE CONNECTED TO EXISTING OUTLET OF THE BUILDING, THE CONTRACTOR IS RESPONSIBLE TO DETERMINATE IF THE ELECTRICAL DEVICES WILL NOT CAUSE EXCESSIVE CONSUMPTION OR DAMAGE ANY EXISTING FUSE BOX, WIRING OR ANY SENSIBLE EXISTING DEVICE . 5. SAFETY MANAGER OR CONTRACTOR SHALL INSPECT ALL ADJOINING EXISTING FLOORING TILES, PAINTS, COVERS, DOOR, WINDOWS, SIGNALS, ELECTRICAL COMPONENTS, LIGHTS, WIRING, DUCTS, PIPES, FURNITURE AND ALL EXISTING ELEMENTS AND AREAS THAT COULD BE DAMAGED OR AFFECTED BY THE RESTORATION / RENOVATION WORKS TO PROVIDE THE NECESSARY PROTECTION TO GUARANTY NO DAMAGE ON THEM 6. CONTRACTOR IS RESPONSIBLE FOR PROTECTING ALL ACCESS AND TRAFFIC AREAS OF THE BUILDING FROM DAMAGE DUE TO MOBILIZATION OF EQUIPMENTS AND MATERIALS DURING THE RENOVATION / RESTORATION WORKS 7. EMERGENCY EXITS SHALL BE PROVIDED DURING WORKS IN CASE OF ANY EMERGENCY EVACUATION OR TRANSPORTATION OF INJURED WORKERS. 8. WORKERS HAVE A DUTY TO TAKE CARE FOR THEIR OWN HEALTH AND SAFETY AND THAT THEY DO NOT ADVERSELY AFFECT THE HEALTH AND SAFETY OF OTHER PERSONS. WORKERS MUST COMPLY WITH ANY INSTRUCTION AND COOPERATE WITH ANY POLICY OR PROCEDURE RELATING TO HEALTH AND SAFETY AT THE WORKPLACE. 9. EMERGENCY PLAN SHOULD BE IN PLACE FOR KNOW TO ADDRESS ANY POSSIBILITY EMERGENCY SUCH AS FIRE RESCUE PLAN 10.IS NOT RECOMMENDED TO STORE HEAVY MATERIALS OR EQUIPMENTS ON ACCESS AREAS, WALKWAYS, STAIRS OR ANYWHERE THAT COULD BLOCK WALKING OR CURRENT OCCUPANCY JOBS. 11.THE CONTRACTOR IS RESPONSIBLE FOR THE RESTORATION SEQUENCES AND SAFETY MEASURES, THE FOLLOWING PROCEDURE AND SAFETY PLAN DESCRIBED IS A RECOMMENDATION RESTORATION SAFETY CONSIDERATION FABRICATION AND ERECTION OF STRUCTURAL STEEL SHALL CONFORM TO THE AISC "MANUAL OF STEEL CONSTRUCTION", 15TH EDITION AND THE AISC "SPECIFICATION FOR STRUCTURAL STEEL BUILDINGS", ANSI/AISC 360-16. STRUCTURAL STEEL PLATES, BRACKETS, SEATS AND OTHER FABRICATION SHALL BE OF STEEL WITH A MINIMUM YIELD STRESS OF 50 KSI. UNLESS OTHERWISE NOTED, ALL BOLTS SHALL DE 3/8" DIAMETER A-325 AND SHALL BE USED IN BEARING TYPE CONNECTIONS. ALL HIGH STRENGTH BOLTS SHALL MEET REQUIREMENTS OF THE "SPECIFICATION FOR STRUCTURAL JOINTS USING ASTM A-325 OR A-490 BOLTS". SHOP AND FIELD WELDING SHALL BE PERFORMED BY CURRENTLY CERTIFIED WELDERS IN ACCORDANCE WITH THE AWS "STRUCTURAL WELDING CODE", LATEST EDITION. ALL WELDED CONNECTIONS SHALL BE E70XX ELECTRODES. SUBMIT STRUCTURAL STEEL AND MISCELLANEOUS FABRICATIONS SHOP AND ERECTIONS DRAWINGS FOR REVIEW BY THE ENGINEER. ANY SPLICES OR CONNECTIONS NOT FULLY PROVIDED IN THESE DRAWINGS SHALL BE DESIGNED BY A DELEGATED ENGINEER WHO OVERSEES THE DETAILING OF THE STEEL SHOP EN ERECTION DRAWINGS. ALL DRAWINGS AND CALCULATIONS SHALL BEAR EBOMSSED SEAL OF A REGISTERED PROFESSIONAL ENGINEER LICENSED IN THE STATE OF FLORIDA. DO NOT USE GAS-CUTTING OF PLASMA CUTTING TORCHES. USE DRILLING OF PUNCHING FOR ALL HOLES. ALL WELDS SHALL BE INSPECTED AND CERTIFIED BY A LICENSED TESTING LAB. STRUCTURAL STEEL NOTES GENERAL NOTES TROPICAL CHEVROLET GARAGE - DOUBLE TEE'S STRUCTURAL REPAIR PLANS 8880 BISCAYNE BLVD., MIAMI SHORES, FL 33138 5/26/2023 S-100PROJECT NAME:CLIENT/OWNER:TROPICAL CHEVROLET GARAGE -DOUBLE TEE'S STRUCTURAL REPAIRPLANSFPV-S231016 MR. VAL BENITEZ8880 BISCAYNE BLVD., MIAMI SHORES, FL33138Sheet No. DRAWING NO. SHEET NAME: DATE: SCALE: DRAWN: CHECKED: APPVD: REVISIONS DATE PROJECT ID: S-100 CA # 29447 782 NW 42ND AVENUE UNIT 635,MIAMI, FL 33126MAIN NUMBER 888-536-1536JOSE M PERALTA, P.E CONEMCO CONSULTANTS FLORIDA P.E. LIC. # 91463 AS SHOWN SM JP JC CONTRACT NO:- BLANK SPACE - CITY STAMP 1. DEMOLISH DAMAGED PORTION OF DOUBLE TEE CONCRETE JOISTS ON FIRST FLOOR 2. FORM AND RE-POUR MISSING PORTION OF CONCRETE JOISTS. 3. PROVIDE STEEL CHANNEL REINFORCEMENT FOR JOISTS. SCOPE OF WORK DRAWINGS LIST S-100 GENERAL NOTES S-200 SHORING PLAN AND SECTIONS S-300 ELEVATIONS S-400 SECTIONS AND DETAILS S-500 DETAILS AERIAL VIEW SCALE: N.T.S.A N TROPICAL CHEVROLET BUILDING DRAFT C10X25 STEEL CHANNEL ANCHORED TO JOISTS W/ 1/2" THRU BOLTS @ 12" O.C & 3" THICK NEW FLANGE POUR TO BE DONE AFTER CHANNEL INSTALLATION EXISTING COLUMN DAMAGE ON COLUMN TO BE REPAIRED AS PER E/S-300 4" X 6" X 6" X 1/4" STEEL ANGLE W/ (2) 3/4" LDT ANCHOR (4.5" MIN EMBED) TO CONCRETE BEAM AND (2) 3/4" THRU-BOLTS TO JOISTS EXISTING CONCRETE BEAM 1/2" THRU BOLTS @ 12" O.C STAGGERED 3" X 3" X 10" X 1/2" STEEL ANGLE ANCHORED TO BEAM W/ (2) 3/4" LDT ANCHORS, 4.5" MIN EMBED. 1'-91 2"3"3" THICK NEW FLANGE POUR TO BE DONE AFTER CHANNEL INSTALLATION 1/2" DIA. X 1-1/2" SHEAR STUDS @ 8" O.C. ALONG CHANNEL C10X25 STEEL CHANNEL ANCHORED TO JOISTS W/ 1/2" THRU BOLTS @ 12" O.C & 4" X 6" X 6" X 1/4" STEEL ANGLE W/ (2) 3/4" LDT ANCHOR (4.5" MIN EMBED) TO CONCRETE BEAM AND (2) 3/4" THRU-BOLTS TO JOISTS CONCRETE TOPPING AND WATERPROOFING BY OTHERS EXISTING CONCRETE BEAM 4" X 4" X 6" X 1/4" STEEL ANGLE W/ (2) 3/4" LDT ANCHOR (4.5" MIN EMBED) TO CONCRETE COLUMN AND (2) 3/4" THRU-BOLTS TO JOISTS EXISTING CONCRETE JOIST EXISTING STEEL ANGLE TO REMAIN EXISTING CONCRETE COLUMN2"21 2"1'-0"#4 @ 12" O.C. BOTH DIRECTIONS ON NEW FLANGE POUR EXISTING STEEL BRACKET TO REMAIN 3" X 3" X 10" X 1/2" STEEL ANGLE ANCHORED TO BEAM W/ (2) 3/4" LDT ANCHORS, 4.5" MIN EMBED. 3" THICK NEW FLANGE POUR TO BE DONE AFTER CHANNEL INSTALLATION 1/2" DIA. X 1-1/2" SHEAR STUDS @ 8" O.C. ALONG CHANNEL C10X25 STEEL CHANNEL ANCHORED TO JOISTS W/ 1/2" THRU BOLTS @ 12" O.C & 4" X 6" X 6" X 1/4" STEEL ANGLE W/ (2) 3/4" LDT ANCHOR (4.5" MIN EMBED) TO CONCRETE BEAM AND (2) 3/4" THRU-BOLTS TO JOISTS NEW WEB POUR TO BE COMPLETED PRIOR TO CHANNEL INSTALLATION EXISTING CONCRETE BEAM 4" X 4" X 6" X 1/4" STEEL ANGLE W/ (2) 3/4" LDT ANCHOR (4.5" MIN EMBED) TO CONCRETE COLUMN AND (2) 3/4" THRU-BOLTS TO JOISTS EXISTING CONCRETE JOIST C10X25 STEEL CHANNEL ANCHORED TO JOISTS W/ 1/2" THRU BOLTS @ 12" O.C & EXISTING CONCRETE COLUMN #4 @ 12" O.C. BOTH DIRECTIONS ON NEW FLANGE POUR 3" X 3" X 7" X 1/2" STEEL ANGLE ANCHORED TO BEAM W/ (2) 3/4" LDT ANCHORS, 4.5" MIN EMBED. 3" X 3" X 10" X 1/2" STEEL ANGLE ANCHORED TO BEAM W/ (2) 3/4" LDT ANCHORS, 4.5" MIN EMBED. CLEAN AND PREPARE SURFACE AS PER MANUFACTURER RECOMMENDATIONS CONC. SLAB COLUMN TIES ELEVATION VIEW DAMAGED PORTION OF COLUMN. CHIP CONCRETE AT A 90° ANGLE AND APPLY SIKAQUICK VOH IN MULTIPLE LIFTS, 1/8" MIN AND 3" MAX LIFT THICKNESS TO CONCRETE SURFACE AND EXPOSED REINFORCING STEEL OR FORM AND POUR CONCRETE AFTER REBAR REPLACEMENT SPLICE AS PERDETAIL B/S-501 OR USEMECHANICAL SPLICESPLICE AS PERDETAIL B/S-501 OR USEMECHANICAL SPLICECUT AND REMOVE DAMAGED REBAR MECHANICAL SPLICING CAN BE USED ADDITIONAL CONCRETE TO BE CHIP AND REPAIR WITH SIKAQUICK VOH SIKA ARMATEC 110 BONDING AGENT BEFORE CONCRETE REPLACEMENT ADD NEW REBAR AS PER DETAIL B/S-501 (WHERE INSTRUCTURED BY ENGINEER) 4"6"1 4" 4"112"3"112"1 4"0'-2" 4" X 4" X 6" X 1/4" STEEL ANGLE 4" X 6" X 6" X 1/4" STEEL ANGLE 6"6"1 4" 4"112"3"112"1 4"2" 3" X 3" X 10" X 1/2" STEEL ANGLE 10"3"12"5"3" 3" X 3" X 7" X 1/2" STEEL ANGLE 7"3"12"2"3"112"PLAN VIEW FLOOR PLAN SCALE: 1/2" = 1'-0"AN 5/26/2023 S-200PROJECT NAME:CLIENT/OWNER:TROPICAL CHEVROLET GARAGE -DOUBLE TEE'S STRUCTURAL REPAIRPLANSFPV-S231016 MR. VAL BENITEZ8880 BISCAYNE BLVD., MIAMI SHORES, FL33138Sheet No. DRAWING NO. SHEET NAME: DATE: SCALE: DRAWN: CHECKED: APPVD: REVISIONS DATE PROJECT ID: S-200 CA # 29447 782 NW 42ND AVENUE UNIT 635,MIAMI, FL 33126MAIN NUMBER 888-536-1536JOSE M PERALTA, P.E CONEMCO CONSULTANTS FLORIDA P.E. LIC. # 91463 AS SHOWN SM JP JC CONTRACT NO:- BLANK SPACE - CITY STAMP SOUTH SIDE REPAIR SECTION SCALE: 3/4" = 1'-0"B NORTH SIDE REPAIR SECTION SCALE: 3/4" = 1'-0"C B S-200 C S-200 C10X25 STEEL CHANNEL ANCHORED TO JOISTS W/ 1/2" THRU BOLTS @ 12" O.C & APPROXIMATE AREA FOR NEW CONCRETE POUR APPROXIMATE AREA FOR NEW CONCRETE POUR 4" X 4" X 6" X 1/4" STEEL ANGLE W/ (2) 3/4" LDT ANCHOR (4.5" MIN EMBED) TO CONCRETE BEAM AND (2) 3/4" THRU-BOLTS TO JOISTS 4" X 4" X 6" X 1/4" STEEL ANGLE W/ (2) 3/4" LDT ANCHOR (4.5" MIN EMBED) TO CONCRETE BEAM AND (2) 3/4" THRU-BOLTS TO JOISTS C10X25 STEEL CHANNEL ANCHORED TO JOISTS W/ 1/2" THRU BOLTS @ 12" O.C & EXISTING CONCRETE COLUMN TO BE REPAIRED AS PER D/S-400 EXISTING CONCRETE BEAM D S-200 SECTION SCALE: 3/4" = 1'-0"D JOIST DAMAGE ON NORTH SIDE OF COLUMN JOIST DAMAGE ON SOUTH SIDE OF COLUMN CONCRETE COLUMN EXPOSED REBAR REPAIR DETAIL SCALE: N.T.S.E STEEL ELEMENTS DETAIL SCALE: 3/4" = 1'-0"F C10X25 STEEL CHANNEL ANCHORED TO JOISTS W/ 1/2" THRU BOLTS @ 12" O.C & NOTES: - JOISTS TO BE SHORED AS SHOWN ON SHORING PLANS BY OTHERS - JOISTS REBARS AND TENDONS TO BE LOCATED (X-RAY SCAN) BEFORE ANCHOR DRILLING TO AVOID CONFLICT. EXISTING STEEL BRACKET BELOW JOIST TO REMAIN EXISTING STEEL BRACKET BELOW JOIST TO REMAIN DRAFT DRAFT