Tropical Chevrolet, 01-25-23 UES No 345425 SPECIAL insp rept #009 (drilled and epoxy dowels) - GDZ + ASProject No.: 2110.2100049
Report No.: 345425
Date: January 25, 2023
STRUCTURAL OBSERVATION REPORT No. SPECIAL-009
CN: GDZ: ASD Page 1 of 8
cc: 1 − Job Site; 1 − Client; 1
The Original of this Report was Signed and Impressed Sealed by the Above Registered Engineer in Accordance with Rule 21H-18.11, Chapter 471, Florida Statute
8050 NW 77th Street · Miami, FL 33166 · P: 305.249.8434 · F: 305.249.8479
Client: Lebolo Construction Management, Inc.
2100 Corporate Drive
Boynton Beach, FL 33426
Project: Tropical Chevrolet Renovation/Expansion
8880 Biscayne Blvd.
Miami Shores, FL 33138
Agent: Gaetano Di Zio, E.I.
Adrian Suarez Diaz
Date of Services: 01/25/2022
Village of Miami Shores Building Permit No: CC-12-20-2951 (issued date 11/07/22, expires 05/08/23)
Scope of Field Services: Professional observation of completed structural elements (Special/Welding Inspector).
Reference Documents:
• JSG structural drawings sheets S1.0 thru S-4.2 (15 pages), Bulleting 7 dated 07/21/2022, signed/sealed by Mark
Johnson FL-PE#51983, reviewed/approved for structural compliance by the Village of Miami Shores Bldg. Dept.
on 08/22, (permit set review by the Miami-Dade County Department of Regulatory and Economic Resources on
05/16/2022).
Record of Field Observations:
Visual verification for the reinforcing steel placement at the following locations indicated below:
1. Continuous wall footings as per S2.0, S1.1 & S4.0/S4.2:
a) Cont. wall footing (with vertical dowels for CMU wall as per note 8) type WF26 along grids A between lines 8 thru
11 completed.
b) Cont. wall footing (with vertical dowels for CMU wall & openings as per note 8 & 9/S4.0 and concrete tie columns
type CC2 [x3]) type WF26 with integrated column pads type F40 (x2) along line 11 between grids A thru E.3
completed.
c) Cont. wall footing (with vertical dowels for CMU wall as per note 8) type WF26 along grids E.2 between lines 8 thru
11 completed.
d) Cont. wall footing (with vertical dowels for CMU wall as per note 9) type WF20 along grids D.1 between lines 11
thru proposed line 12 completed.
e) Cont. wall footing (with vertical dowels for CMU wall as per note 9) type WF20 along proposed line 12 between
grids D.1 thru D.6 completed.
f) Cont. wall footing (with vertical dowels for CMU wall as per note 8) type WF26 along grids D.6 between lines 11
thru proposed line 12 completed.
2. Column pad footings as per S2.0, S1.1 & S4.0/S4.2:
a) Column footings type F66 at grid-lines B.8x9 & D.5x9 completed (*).
b) Column footings type F90 at grid-lines B.8x10 & D.5x10 completed (*).
The above mentioned reinforcing steel placement was found to be performed in substantial compliance with the referenc e
documents except (see below ↓↓↓ *)
(*) as per S1.1 “column / base plate schedule: the bottom hex nut shall be “tack welded secured”. SUNCOR did not include
a clarification/approval question for omission of the tack weld under dwg. Sheet AB1 “approver note”. As per approver note
#2 a plate washer was approved above the previously mentioned hex nut. This plate was found to be loose (floating) not
secured preventing displacement at the time of conc. placement. GC to provide clarification for the observed AS BUILT
conditions. For items 2g & 2h.
DRAFT
Project No.: 2110.2100049
Report No.: 345425
Date: January 25, 2023
STRUCTURAL OBSERVATION REPORT No. SPECIAL-009
CN: GDZ: ASD Page 2 of 8
cc: 1 − Job Site; 1 − Client; 1
The Original of this Report was Signed and Impressed Sealed by the Above Registered Engineer in Accordance with Rule 21H-18.11, Chapter 471, Florida Statute
8050 NW 77th Street · Miami, FL 33166 · P: 305.249.8434 · F: 305.249.8479
3. Visual verification of the reinforcing steel placement at the following locations indicated below:
a) 8”/12” thick CMU stem wall along grids “A” and “E.2” between lines “8” thru ”11”, along line “11” between grids “A”
thru “E.2”, along grids “D.1” and “D.6” between lines “11” thru “12” and along line “12” between grids “D.1” thru
“D.6”, from elevation approx. −2'−0" to 0’−0”, as per S1.0, S2.0, S2.2, 2/S3.1, 1/S3.2, S4.0/details 1, 3 & 5, 7/S4.1
and attached clarification submitted by the SEoR via e-mail, as we addressed on UES Structural Observation
Reports No. 004 (No.: 341925) dated 12/02/2022 and No. 006 (No.: 342202) dated 12/05/2022, 2nd re-inspection
completed:
➢ Some reinforcing steel was found to be deformed.
➢ Five (5) courses (approx. elev. +3'−4") were found to be laid on top of the stem wall.
➢ Missing/over spaced vertical reinforcing steel at some locations.
➢ Debris (chunks of masonry) was found in the CMU cells.
➢ Missing masonry interlocking of CMU wall at gridlines E.2x11 and D.6x12.
➢ Missing CMU control joint (partial) at gridline D.3x11.
➢ Missing neoprene pre-formed gasket at CMU control joints, as per 1/S1.0. To be provided for the 1st lift.
➢ Vertical dowels were found not to meet the minimum lap splice length of 48 Ø bar, as per S1.0/Masonry Note
M11.
➢ CMU reinforced filled cells head joints were found not to be aligned and obstructed approx. gridline E.2x8.1, as
per S1.0/Masonry Note M6.
➢ CMU horizontal reinforcement (ladder) was found not to extended into concrete tie column, as per
S1.0/Masonry Note M7.
b) CIP concrete tie column mark CC2 (12"x24") at gridlines B.8x11 and D.5x11, 1st lift from elevation −2'−0" (top of
footing) to 0'−0", as per S1.0, S1.1/Concrete Tie Column Schedule, S2.0 and 4/S4.0, as we addressed on UES
Structural Observation Report No. 006 (No.: 342202) dated 12/05/2022, re-inspection completed:
➢ Reinforcing steel was found not to meet the minimum concrete cover of 1½”, as per 4/S4.0.
➢ CMU horizontal reinforcement (ladder) was found not to extended into concrete tie column, as per
S1.0/Masonry Note M7. DRAFT
Project No.: 2110.2100049
Report No.: 345425
Date: January 25, 2023
STRUCTURAL OBSERVATION REPORT No. SPECIAL-009
CN: GDZ: ASD Page 3 of 8
cc: 1 − Job Site; 1 − Client; 1
The Original of this Report was Signed and Impressed Sealed by the Above Registered Engineer in Accordance with Rule 21H-18.11, Chapter 471, Florida Statute
8050 NW 77th Street · Miami, FL 33166 · P: 305.249.8434 · F: 305.249.8479
c) CIP concrete tie column mark CC2 (12"x24") at gridline E.5x11, 1st lift from elevation −2'−0" (top of footing) to 0'−0",
as per S1.0, S1.1/Concrete Tie Column Schedule, S2.0 , 4/S4.0 and attached clarification submitted by the SEoR
via e-mail, completed.
Explanatory Note:
➢ Drilled and epoxy vertical rebar dowels into existing concrete foundation were done by others prior to today’s
site visit (a UES representative did not verify any drilled holes for cleanness, embedment, epoxy application
and rebar dowels installation).
The reinforcing steel placement at the locations mentioned above was found to be in substantial compliance with the
reference documents.
4. Visual verification of drilled holes for post-installed rebar dowels by means of approved anchoring epoxy Hilti HIT-HY
200 at the following locations indicated below:
a) Cleanness/depth check (9” min. embedment) and epoxy application for #5 horizontal rebar dowels into existing two
(2) CIP concrete footings, as per sheet S1.0 R, as we addressed on UES Structural Observation Report No. 08
(No.: 345306) dated 01/23/2023, re-inspection completed:
➢ Drilled holes were found not to meet the minimum embedment.
b) Cleanness/depth check (6” min. embedment) and epoxy application for #5 horizontal rebar dowels into existing CIP
concrete slab on grade along grid “E” between lines “5” thru “8”, as per 3/S4.2, as we addressed on UES Structural
Observation Report No. 08 (No.: 345306) dated 01/23/2023, re-inspection preliminary:
➢ Drilled holes were found to be the same diameter as the rebars to be epoxied.
➢ Pending application of anchoring epoxy Hilti HIT-HY 200.
c) Cleanness/depth check (9” min. embedment) and epoxy application for #5 horizontal rebar dowels into existing CIP
concrete footings at gridlines B.8x9 and B.8x10, as per attached drawing No. SK-01-17-23, completed.
d) Cleanness/depth check (9” min. embedment) and epoxy application for #5 horizontal rebar dowels into existing CIP
concrete footings at gridlines D.3x9 and D.3x10, as per attached drawing No. SK-01-17-23, preliminary:
➢ Pending application of anchoring epoxy Hilti HIT-HY 200.
Mr. Jim Jenco, Project Superintendents with Lebolo Construction, was notified of the aforementioned visual verification
results.
Please see adjacent report pages for photographs.
DRAFT
Project No.: 2110.2100049
Report No.: 345425
Date: January 25, 2023
STRUCTURAL OBSERVATION REPORT No. SPECIAL-009
CN: GDZ: ASD Page 4 of 8
cc: 1 − Job Site; 1 − Client; 1
The Original of this Report was Signed and Impressed Sealed by the Above Registered Engineer in Accordance with Rule 21H-18.11, Chapter 471, Florida Statute
8050 NW 77th Street · Miami, FL 33166 · P: 305.249.8434 · F: 305.249.8479
DRAFT
Project No.: 2110.2100049
Report No.: 345425
Date: January 25, 2023
STRUCTURAL OBSERVATION REPORT No. SPECIAL-009
CN: GDZ: ASD Page 5 of 8
cc: 1 − Job Site; 1 − Client; 1
The Original of this Report was Signed and Impressed Sealed by the Above Registered Engineer in Accordance with Rule 21H-18.11, Chapter 471, Florida Statute
8050 NW 77th Street · Miami, FL 33166 · P: 305.249.8434 · F: 305.249.8479
DRAFT
Project No.: 2110.2100049
Report No.: 345425
Date: January 25, 2023
STRUCTURAL OBSERVATION REPORT No. SPECIAL-009
CN: GDZ: ASD Page 6 of 8
cc: 1 − Job Site; 1 − Client; 1
The Original of this Report was Signed and Impressed Sealed by the Above Registered Engineer in Accordance with Rule 21H-18.11, Chapter 471, Florida Statute
8050 NW 77th Street · Miami, FL 33166 · P: 305.249.8434 · F: 305.249.8479
DRAFT
Project No.: 2110.2100049
Report No.: 345425
Date: January 25, 2023
STRUCTURAL OBSERVATION REPORT No. SPECIAL-009
CN: GDZ: ASD Page 7 of 8
cc: 1 − Job Site; 1 − Client; 1
The Original of this Report was Signed and Impressed Sealed by the Above Registered Engineer in Accordance with Rule 21H-18.11, Chapter 471, Florida Statute
8050 NW 77th Street · Miami, FL 33166 · P: 305.249.8434 · F: 305.249.8479
DRAFT
Project No.: 2110.2100049
Report No.: 345425
Date: January 25, 2023
STRUCTURAL OBSERVATION REPORT No. SPECIAL-009
CN: GDZ: ASD Page 8 of 8
cc: 1 − Job Site; 1 − Client; 1
The Original of this Report was Signed and Impressed Sealed by the Above Registered Engineer in Accordance with Rule 21H-18.11, Chapter 471, Florida Statute
8050 NW 77th Street · Miami, FL 33166 · P: 305.249.8434 · F: 305.249.8479
Reviewed by:
Universal Engineering Sciences
Certificate of Authorization No. 549
Carlos Naumann, P.E., S.I.
Florida Professional Engineer No. 18594
Florida Special Inspector No. 181
DRAFT
DRAFT