Tropical Chevrolet, 01-25-23 UES Inspection Log, SPECIAL insp rept #009cc: 1 – Client, 1 – Job Site Page 1 of 3
Item
No.
UES
Report
No.
Inspection
Date &
Inspector
Description of work inspected Result of
Inspection
Date of Re-
inspection &
Inspector
1 SP#01
(341224)
11/17/2022
Humberto Carvajal,
CWI.
1. Continuous wall footings as per S2.0, S1.1 & S4.0/S4.2:
a) Cont. wall footing (with vertical dowels for CMU wall as per note 8) type WF26 along
grids A between lines 8 thru 11.
b) Cont. wall footing (with vertical dowels for CMU wall & openings as per note 8 & 9/S4.0
and concrete tie columns type CC2 [x3]) type WF26 with integrated column pads type
F40 (x2) along line 11 between grids A thru E.3.
c) Cont. wall footing (with vertical dowels for CMU wall as per note 8) type WF26 along
grids E.2 between lines 8 thru 11.
d) Cont. wall footing (with vertical dowels for CMU wall as per note 9) type WF20 along
grids D.1 between lines 11 thru proposed line 12.
e) Cont. wall footing (with vertical dowels for CMU wall as per note 9) type WF20 along
proposed line 12 between grids D.1 thru D.6.
f) Cont. wall footing (with vertical dowels for CMU wall as per note 8) type WF26 along
grids D.6 between lines 11 thru proposed line 12.
2. Column pad footings as per S2.0, S1.1 & S4.0/S4.2:
g) Column footings type F66 at grid-lines B.8x9 & D.5x9 in progress (*).
h) Column footings type F90 at grid-lines B.8x10 & D.5x10 in progress (*).
Pending
PASS
11/18/22
HC
Partially completed
Pending re-inspection
11/30/22
HC
2
SP#02
(341357)
11/18/2022
Humberto Carvajal,
CWI.
1. Continuous wall footings as per S2.0, S1.1 & S4.0/S4.2:
a) Cont. wall footing (with vertical dowels for CMU wall as per note 8) type WF26 along
grids A between lines 8 thru 11 completed (**).
b) Cont. wall footing (with vertical dowels for CMU wall & openings as per note 8 & 9/S4.0
and concrete tie columns type CC2 [x3]) type WF26 with integrated column pads type
F40 (x2) along line 11 between grids A thru E.3 completed.
c) Cont. wall footing (with vertical dowels for CMU wall as per note 8) type WF26 along
grids E.2 between lines 8 thru 11 completed (**).
Partial
(see 11/23/22)
INSPECTION LOG UNIVERSAL ENGINEERING SCIENCES
PROJECT: Tropical Chevrolet Renovation & Expansion Date: December 6, 2022
PROJECT LOCATION: 8880 Biscayne Blvd., Miami Shores, FL 33138 UES PROJECT. NO.: 2110.2100049
CLIENT: Lebolo Construction Management, Inc. CONTRACTOR: Lebolo Construction
ENG. OF RECORD: Mark Johnson FL-PE#51983 with JSG PERMIT #: CC-12-20-2951
THRESHOLD ENG: n/a UES Certificate of Authorization 000549
cc: 1 – Client, 1 – Job Site Page 2 of 3
Item
No.
UES
Report
No.
Inspection
Date &
Inspector
Description of work inspected Result of
Inspection
Date of Re-
inspection &
Inspector
SP#02
(341357)
11/18/2022
Humberto Carvajal,
CWI
d) Cont. wall footing (with vertical dowels for CMU wall as per note 9) type WF20 along
grids D.1 between lines 11 thru proposed line 12 completed.
e) Cont. wall footing (with vertical dowels for CMU wall as per note 9) type WF20 along
proposed line 12 between grids D.1 thru D.6 completed.
f) Cont. wall footing (with vertical dowels for CMU wall as per note 8) type WF26 along
grids D.6 between lines 11 thru proposed line 12 completed.
2. Column pad footings as per S2.0, S1.1 & S4.0/S4.2:
a) Column footings type F66 at grid-lines B.8x9 & D.5x9 completed (*).
b) Column footings type F90 at grid-lines B.8x10 & D.5x10 completed (*).
The above mentioned reinforcing steel placement was found to be performed in substantial
compliance with the reference documents except (see below ↓↓↓ *, **, ***)
(*) as per S1.1 “column / base plate schedule: the bottom hex nut shall be “tack welded secured”.
SUNCOR did not include a clarification/approval question for omission of the tack weld under
dwg. Sheet AB1 “approver note”. As per approver note #2 a plate washer was approved above
the previously mentioned hex nut. This plate was found to be loose (floating) not secured
preventing displacement at the time of conc. placement. GC to provide clarification for the
observed AS BUILT conditions. For items 2g & 2h.
(**) required [if applicable] drilled & epoxy dowels missing as per 1/S4.2 for items 1a & 1c.
(**) installation of the additional reinforcing for the proposed “MCJ” was found to be missing at
the time of this site visit as per 1/S1.0 for items 1a thru 1h.
↑↑↑
↓↓↓
←←←
3 SP#03
(341409)
11/23/2022
Humberto Carvajal,
CWI.
ITEMS 1a thru 1f COMPLETED.
ITEMS 2a & 2b pending clarification and/or approval from the SEoR. Partial N/A
4
SP#04 (341925)
SP#06 (342202)
SP#07 (342311)
11/30/2022
12/05/2022
12/06/2022
Gaetano Di Zio, E.I.
1. Visual verification of the reinforcing steel placement at the following locations indicated
below:
a) 8”/12” thick CMU stem wall along grids “A” and “E.2” between lines “8” thru ”11”,
along line “11” between grids “A” thru “E.2”, along grids “D.1” and “D.6” between lines
“11” thru “12” and along line “12” between grids “D.1” thru “D.6”, from elevation
approx. −2'−0" to 0’−0”.
Failed
Reinspection
Failed
Pass
12/06/22. See Insp.
Rept. #07 for details
G. Di Zio
5 SP#05
(342087)
12/02/2022
Gaetano Di Zio, E.I. Construction Meeting N/A
6 SP#06 (342202)
SP#07 (342311)
12/05/2022
12/06/2022
Gaetano Di Zio, E.I.
1. Visual verification of the reinforcing steel placement at the following locations indicated
below:
Failed
Pass
12/06/22. See Insp.
Rept. #07 for details
G. Di Zio
cc: 1 – Client, 1 – Job Site Page 3 of 3
Item
No.
UES
Report
No.
Inspection
Date &
Inspector
Description of work inspected Result of
Inspection
Date of Re-
inspection &
Inspector
b) CIP concrete tie column mark CC2 (12"x24") at gridlines B.8x11 and D.5x11, from
elevation −2'−0" (top of footing) to 0'−0".
7 SP#07
(342311)
12/06/2022
Gaetano Di Zio, E.I.
1. Visual verification of the reinforcing steel placement at the following locations indicated
below:
a) CIP concrete tie column mark CC2 (12"x24") at gridline E.2x11, from elevation −2'−0"
(top of footing) to 0'−0".
Pass
8 SP#08
(345306)
01/23/2023
Gaetano Di Zio, E.I.
Adrian Suarez Diaz
1. Visual verification of drilled holes for post-installed rebar dowels by means of approved
anchoring epoxy:
a) Cleanness/depth check (9” min. embedment) and epoxy application for #5 horizontal
rebar dowels into existing two (2) CIP concrete footings.
Failed
Pass
01/25/22. See Insp.
Rept. #09 for details
G. Di Zio
b) Cleanness/depth check (6” min. embedment) and epoxy application for #5 horizontal
rebar dowels into existing CIP concrete slab on grade along gird “E” between lines “5”
thru “8”
Failed
Preliminary
9 SP#09
(345425)
01/25/2023
Gaetano Di Zio, E.I.
Adrian Suarez Diaz
1. Visual verification of drilled holes for post-installed rebar dowels by means of approved
anchoring epoxy:
a) Cleanness/depth check (9” min. embedment) and epoxy application for #5 horizontal
rebar dowels into existing CIP concrete footings at gridlines B.8x9 and B.8x10.
Pass
b) Cleanness/depth check (9” min. embedment) and epoxy application for #5 horizontal
rebar dowels into existing CIP concrete footings at gridlines D.3x9 and D.3x10. Preliminary