Inspection Worksheet
Miami Shores Village
10050 N.E.2nd Avenue Miami Shores, FL
Phone: (305)795-2204 Fax: (305)756-8972
Inspection Number: INSP-249546 PermitNumber: PLC-11-14-2598
Scheduled Inspection Date: December 22,2015 Permit Type: Plumbing - Commercial
Inspector: Diaz, Osvaldo
Inspection Type: Piping
Owner: ,BARRY UNIVERSITY Work Classification: New
Job Address:11300 NE 2 Avenue
Miami Shores,FL 33138-0000 Phone Number
Parcel Number 1121360000050
Project: <NONE>
Contractor: HG CONSTRUCTION DEVELOPMENT&INVESTMENT,INC Phone: (786)845-8999
Building Department Comments
PROJECT CONSISTS OF APPROXIMATELY 2,100 LINEAL Infractio Passed Comments
FEET OF PROPOSED, PRIVATE GRAVITY SANITARY INSPECTOR COMMENTS False
SEWER MAIN EXTENSION TO SERVICE 6 EXISTING
BUILDINGS THAT ARE CURRENTLY CONNECTED TO
SEPTIC TANK SYSTEMS. THE EXISTING SEPTIC TANK
AND ASSOCIATED DRAIN FIELDS WILL BE
DEMOLISHED/ABANDONED AND SEWER SERVICE
TRANSFERRED.
Inspector Comments
P s d L-i
Failed
Correction ❑
Needed
Re-Inspection ❑
Fee
No Additional Inspections can be scheduled until
re-inspection fee is paid
December 21,2015 For Inspections please call: (305)762-4949 Page 25 of 33
Kimley ))) Horn
CONSTRUCTION OBSERVATION REPORT
Client: Site Location: Project Name:
Barry University 11300 NE 2nd Avenue,Miami Shore,FL 33161 Septic to Sewer
Site Visit Purpose:Construction progress Time: Date: Pass/Fail:
N/A 12/17/2015 N/A
Present on Site:
1. Michael Marrero-Kimley-Horn and Associates
2. Jose Rivera-Kimley-Horn and Associates
3. Al Garcia—HG Construction
4. Carlos-HG Construction
Comments/Notes:
• MH-7 was installed and connected to pipe.-12/16/15
• Approximately 80 LF of sewer pipe were installed towards MH-6.-12/16/15
• Excavating and placing 8"pipe south towards S-6.—12/17/15
Request For Information:
Page 1 of 4
Kimley ))) Horn CONSTRUCTION OBSERVATION REPORT
Client: Site Location: Project Name:
Barry University 11300 NE 2nd Avenue, Miami Shore, FL 33161 Septic to Sewer
Description: Installation of MH-7 with grout seal around 8-inch Direction: Date: Photo:
pipe to south. North 12/16/2015 1
rs
a
x
v R>
Description: Excavation and installation of pipe between MH-7 to Direction: Date: Photo:
MH-6. North 12/16/2015 2
ri
'aS1yr' � li i
Page 2 of 4
Kimley ))) Horn CONSTRUCTION OBSERVATION REPORT
Client: Site Location: Project Name:
Barry University 11300 NE 2"d Avenue, Miami Shore, FL 33161 Septic to Sewer
Description: Excavation and installation of pipe between MH-7 to Direction: Date: Photo:
MH-6. North 12/17/2015 3
7S
.3• "c.97- fit
a
t
d i
Description: Excavation near MH-6 proposed location. Direction: Date: Photo:
North 12/17/2015 4
•,s
y
Page 3 of 4
END OF REPORT
Kimley ))) HornCONSTRUCTION OBSERVATION REPORT
Client: Site Location: Project Name:
Barry University 11300 NE 2"d Avenue, Miami Shore,FL 33161 Septic to Sewer
Site Visit Purpose:Construction progress Time: Date: Pass/Fail:
2:50 PM-3:30 PM 1 12/18/2015 N/A
Present on Site:
1. Michael Marrero-Kimley-Horn and Associates
2. Jose Rivera-Kimley-Horn and Associates
3. Carlos-HG Construction
Comments/Notes:
• MH-7 was installed and connected to pipe.
• Pipe from MH-6 to MH-7 was approximately 90%installed and covered but not connected to MH-6.
• MH-6 was set approximately 5-feet north of the proposed plan location to avoid conflict w/existing utilities.
Request For Information:
Pagel of 8
Kimley ))) Horn CONSTRUCTION OBSERVATION REPORT
Client: Site Location: Project Name:
Barry University 11300 NE 2nd Avenue, Miami Shore, FL 33161 Septic to Sewer
Description: Excavation ad backfill of road between MH-7 to MH- Direction: Date: Photo:
6. South 12/18/2015 1
j f
Description: Installation of MH-7 with grout seal around 8-inch Direction: Date: Photo:
pipe to south. North 12/18/2015 2
.i..r
k
� � F •re
�ya
Page 2 of 8
Kimley ))) HornCONSTRUCTION OBSERVATION REPORT
Client: Site Location: Project Name:
Barry University 11300 NE 2"d Avenue, Miami Shore, FL 33161 Septic to Sewer
Description: Grout seal around 8-inch pipe to south of MH-7. Direction: Date: Photo:
Northeast 12/18/2015 3
77
f � 1�
Description: Excavation and backfill around MH-7 Direction: Date: Photo:
North 12/18/2015 4
a
t
Page 3 of 8
Kimley ))) HornCONSTRUCTION OBSERVATION REPORT
Client: Site Location: Project Name:
Barry University 11300 NE 2nd Avenue, Miami Shore, FL 33161 Septic to Sewer
Description: Backfill over pipe between MH-7 to MH-6. Direction: Date: Photo:
South 12/18/2015 5
V
uZa az
Description: Excavation and installation of MH-6 and pipe Direction: Date: Photo:
between MH-7 to MH-6. North 12/18/2015 6
r.
,y
I.
Page 4 of 8
Kimley ))) Horn CONSTRUCTION OBSERVATION REPORT
Client: Site Location: Project Name:
Barry University 11300 NE 2nd Avenue, Miami Shore, FL 33161 Septic to Sewer
Description: Excavation of pipe between MH-7 to MH-6. Existing Direction: Date: Photo:
utility crossing just north of MH-6. Southwest 12/18/2015 7
L.
x
'A
Description:
Description: Excavation of pipe between MH-7 to MH-6. Existing Direction: Date: Photo:
utility crossing just north of MH-6. South 12/18/2015 8
I �
.�I
Ir
t
Mk:
Page 5 of 8
Kimley ))) Horn CONSTRUCTION OBSERVATION REPORT
Client: Site Location: Project Name:
Barry University 11300 NE 2nd Avenue, Miami Shore, FL 33161 Septic to Sewer
Description: Excavation and installation of MH-6 and pipe Direction: Date: Photo:
between MH-7 to MH-6. North 12/18/2015 9
JW
r {
Description: Excavation and installation of MH-6 and pipe Direction: Date: Photo:
between MH-7 to MH-6. North 12/18/2015 10
u
f
f
Page 6 of 8
Kimley ))) Horn CONSTRUCTION OBSERVATION REPORT
Client: Site Location: Project Name:
Barry University 11300 NE 2"d Avenue, Miami Shore, FL 33161 Septic to Sewer
Description: Excavation and installation of pipe between MH-7 to Direction: Date: Photo:
MH-6. North 12/18/2015 11
Page 7 of 8
END OF REPORT